Sample report · Capital Project Oversight
We re-derived a published figure from the public record.
We gave SectorPrompts only the Denver VA hospital's initial budget and the documented scope growth from a public GAO report — and withheld the cost-growth percentage and the final price tag. It came back with a 427% cost increase on a $1.73 billion project, matching GAO's published table exactly — the headline figures reconciled to GAO's own numbers.
The situation
A megaproject blow-out, turned into a defensible oversight report.
A congressional oversight committee or agency inspector general needs a megaproject's cost blow-out turned into a clean, defensible report. The Denver VA hospital in Aurora, Colorado is the textbook case — the U.S. Government Accountability Office documented it in detail.
We used it as a reconcile test: feed the public inputs, withhold the answer, and see whether the report re-derives the auditor's published number from those inputs alone.
What we supplied
Only public inputs — each one sourced.
We typed in the numbers a human would pull straight off the GAO report. We deliberately omitted the cost-growth percentage and the revised total, so the app had to derive them.
| Input | Value | Source |
|---|---|---|
| Asset class | Vertical building (institutional hospital) | Denver VA Medical Center |
| Delivery method | Integrated design & construction | VA's stated delivery method |
| Oversight concern | Cost overrun & forecast at completion | — |
| Initial contract value | $328,000,000 | GAO Table 1 (2004 baseline) |
| Documented scope / change-order growth | $1,402,000,000 | GAO Table 1 (current − initial) |
Source: GAO-15-564T · download the source document we used.
The report
The finished, board-ready output.
This is the actual rendered report — interactive charts and all. Nothing was edited after generation.
Reconcile
Our output vs. the published figures.
| Metric | Published | Ours (computed) | Match | Note |
|---|---|---|---|---|
| Cost-growth % | 427% | 427.4% (1,402M ÷ 328M) | ✓ exact | Withheld from the app — it derived it |
| Revised total estimate | $1.73 billion | $1,730,000,000 | ✓ exact | Derived: initial + change orders |
| Initial estimate | $328M | $328,000,000 | ✓ | Carried through |
Earned-value figures (CPI, SPI, forecast-at-completion) are modeled estimates, clearly labeled in the report and kept distinct from the reconciled cost-growth figure — GAO doesn't publish raw earned-value data. The cost growth is the hard reconcile, and it's exact.
Build the same report from your own numbers.
You supply the figures you already have, and every number comes back labeled by where it came from — so you can put your name on it and show your work.