Sample report · Capital Project Oversight

We re-derived a published figure from the public record.

We gave SectorPrompts only the Denver VA hospital's initial budget and the documented scope growth from a public GAO report — and withheld the cost-growth percentage and the final price tag. It came back with a 427% cost increase on a $1.73 billion project, matching GAO's published table exactly — the headline figures reconciled to GAO's own numbers.

The situation

A megaproject blow-out, turned into a defensible oversight report.

A congressional oversight committee or agency inspector general needs a megaproject's cost blow-out turned into a clean, defensible report. The Denver VA hospital in Aurora, Colorado is the textbook case — the U.S. Government Accountability Office documented it in detail.

We used it as a reconcile test: feed the public inputs, withhold the answer, and see whether the report re-derives the auditor's published number from those inputs alone.

What we supplied

Only public inputs — each one sourced.

We typed in the numbers a human would pull straight off the GAO report. We deliberately omitted the cost-growth percentage and the revised total, so the app had to derive them.

InputValueSource
Asset classVertical building (institutional hospital)Denver VA Medical Center
Delivery methodIntegrated design & constructionVA's stated delivery method
Oversight concernCost overrun & forecast at completion
Initial contract value$328,000,000GAO Table 1 (2004 baseline)
Documented scope / change-order growth$1,402,000,000GAO Table 1 (current − initial)

Source: GAO-15-564T · download the source document we used.

The report

The finished, board-ready output.

This is the actual rendered report — interactive charts and all. Nothing was edited after generation.

Open the report full-screen ↗

Reconcile

Our output vs. the published figures.

MetricPublishedOurs (computed)MatchNote
Cost-growth % 427% 427.4% (1,402M ÷ 328M) ✓ exact Withheld from the app — it derived it
Revised total estimate $1.73 billion $1,730,000,000 ✓ exact Derived: initial + change orders
Initial estimate $328M $328,000,000 Carried through

Earned-value figures (CPI, SPI, forecast-at-completion) are modeled estimates, clearly labeled in the report and kept distinct from the reconciled cost-growth figure — GAO doesn't publish raw earned-value data. The cost growth is the hard reconcile, and it's exact.

Build the same report from your own numbers.

You supply the figures you already have, and every number comes back labeled by where it came from — so you can put your name on it and show your work.